KSEB Post Shifting Charges|Application,Fee,Procedures,|KSEB

     In this article, let's create a basic idea about KSEB Post Shifting Charges.In addition with basic material and labour cost, 16% Material SOC and 10 % Supervision Charges are need to be paid,Also  GST (18%) is applicable. 

1.First you need to submit a written request to concerned Assistant Engineer.

2.Then you  have to pay required fee(Application and Processing Fees) under the service"Realignment of Existing Service Wire/Post "or "Realignment of Existing Service Wire/Post-HT "   

Fee:-

LT-Rs.354/-

HT-Rs.1180/-

 3.With in a week assigned person will visit your premises and prepare an Estimate and Sketch of the required shifting ,if possible.

4.Then you will be notified regarding the Estimate Cost.

5.After fee payment,the work will carried out by External Agencies. 

Here,we discuss about the Shifting of a LT Pole and Line .

The task required are:-

1.Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same.-Rs.1280/-

2.Dismantling (without damage) LT stay incl. digging pit in all classes of soil and backfilling-Rs.312/-

3. Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls.-Rs.247.60/-(.05km)

4. Erecting one LT PSC Pole in position incl. digging &
back filling pit.-Rs.1342/-

5. Providing Stay for LT poles incl. digging & back filling pit.-Rs.625/-

6. Stringing one km LT Sph 2 wire line (Rabbit) incl. fitting cross arm etc. removing touchings and conveyance of materials.-Rs.507.47/-(.045km)

Total Labour charge-Rs.4314.07/-

Super vision Charge10%-Rs.431.41/-

GST(18%)-Rs.854.13/-

Total Estimate Cost-Rs.5602/-

 

 

 

 

 

 

 

 


                                     