Case1
Then
ECSC=₹5540
CGST(9%)+SGST(9%)=₹997.2
You have to add normal(WP) charges with this.
1.₹2054 (Single Phase )
2.₹4980(There Phase )
So Total ECSC=5540+997.2+2054=₹8592.
(Single Phase ).
This will applicable in all the following cases.
Here the basic ECSC rate=₹9160
In addition to this ₹80 per meter.
Suppose the length of OH line =40 meters
Then total cost is calculated as follows :
9160+80*40=₹12360
GST(SGST(9%)+CGST(9%)-18%=₹2224.8
Total =₹14585
The basic rates as follows, you have to pay GST(18%) in addition to the amount shown here.
Pole insertion with stay-₹8170.
Here the basic ECSC rate=₹21950
In addition to this ₹80 per meter for length above 50 meters .
Suppose the length of OH line =90 meters
Then total cost is calculated as follows :
21950+80*40=₹25150
GST(SGST(9%)+CGST(9%)-18%=₹4527
Total =₹29677
2.Pole insertion in three phase line with stay -₹9200.
3.Pole insertion in three phase line without stay -₹7730.